What this is, and what it is not
A roadmap sets out which approvals apply to your facility, in what order, what each one needs from the plan, and how long to allow. It is planning input for the business case and the programme. We do not submit applications on your behalf, and we do not give legal advice. Where a point turns on the law, we say so and recommend you take it to a Saudi lawyer.
Why it belongs in the plan
Approvals shape the facility as much as demand does. The facility type decides who may own it, which staff must be Saudi, what the building has to provide and when the licence can be issued. Getting one of these wrong late in design is expensive, and getting it wrong in the model makes the opening date and the ramp-up unreliable.
The steps we map
Ownership and investment registration
Foreign investors may own hospitals, general polyclinics and telemedicine centres outright [1], while single-specialty clinics must be owned by a Saudi physician in the relevant field [2]. The rules for other facility types were amended again in 2023 [3], which is why we check them for each project.
MoH preliminary approval and final licence
Private facilities are licensed through the Ministry's Seha platform [4] [5]. Preliminary approval is immediate for most activities, but not for private hospitals, one-day surgery centres, addiction centres, telemedicine centres or independent home medical services [6]. Facilities outside the immediate-licence list need a visit from an inspection committee before the final licence is issued [7].
Key staff
A hospital needs a qualified Saudi medical director and a Saudi managing director [4], and each role has its own Saudisation rate [8] [9].
Accreditation
The Saudi Central Board for Accreditation of Healthcare Institutions (CBAHI) is the national accreditation body for government and private facilities, and the Ministry requires facilities to apply its standards [10]. Building to those standards from the start avoids changes later.
Insurers
Most private revenue comes from insured patients. A facility applies to the Council of Health Insurance for accreditation once it holds its final licence [11], and only then can it join insurers' networks, so the time from opening to the first insurer contracts belongs in the ramp-up.
What you receive
- A roadmap of approvals in order, with what each needs and an indicative duration.
- A requirements checklist for the plan and the design brief.
- The approval-related assumptions for the financial model.
- A list of points to confirm with your Saudi lawyer.
Questions we're asked
Will you apply for the licence for us?
No. We plan for the approvals and set out what each needs. Applications are made by you, your lawyer or a licensing agent.
Do the rules change often?
They have changed several times since 2019, especially on ownership. We check the current position for each project and date every rule we cite.
Is CBAHI the same as JCI?
No. CBAHI is the Saudi national accreditation body. Some private hospitals also seek international accreditation, which is a separate choice.
Sources
- Oxford Business Group, Private expansion: regulatory reforms and targeted PPPs strengthen private sector participation, 2025
- Simmons & Simmons, Foreign investment relaxation in the Saudi healthcare sector, January 2019
- Saudi Gazette, Owner of private health firms must be full-time Saudi doctor, February 2023
- Ministry of Health, Healthcare Investor Licensing Guide
- Ministry of Health, Healthcare Licensing Services
- Hazim Al Madani Law Firm, Investors' health licenses in Saudi Arabia
- Ministry of Health, FAQs for Healthcare Licensing Service
- Argaam, HRSD Ministry decides to raise Saudization rates in 269 private sector professions, January 2025
- Arab News, First phase of Saudization in healthcare professions starts today, April 2025
- Ministry of Health, CBAHI and MOH symposium on clinical audit, February 2015
- Zavis, How to open a clinic in Saudi Arabia (licensing steps on Seha and CHI accreditation)