1. Decide who will own it
Ownership is the first question because it decides who applies for everything else. Foreign investors were allowed to own hospitals in Saudi Arabia before other health facilities [1], and may now own hospitals, general polyclinics and telemedicine centres outright [2]. Single-specialty clinics still have to be owned by a Saudi physician in the relevant field [1], and further conditions for some facility types were added in 2023 [3]. If your hospital will include affiliated clinics or a separate day surgery centre, check each one.
Under the Investment Law and its implementing regulations, foreign investors now register with the Ministry of Investment (MISA) rather than applying for an investment licence [4]. Registration and a commercial registration come before the Ministry of Health application.
2. Preliminary approval from the Ministry of Health
Private health facilities are licensed through the Ministry of Health's Seha platform [5]. For most activities, preliminary approval is issued automatically, but private hospitals are among the exceptions, along with one-day surgery centres, addiction centres, telemedicine centres and independent home medical services [6]. A hospital's preliminary approval is therefore reviewed, and the plan you submit should already be consistent: site, services, bed numbers and the ownership structure.
The Ministry publishes an investor guide to health facility licensing, most recently updated in 2023 [7]. It is the best single starting point for the current requirements.
3. Design, build and recruit to the licence
Between preliminary approval and opening, the hospital is designed, built, equipped and staffed to meet the requirements of its licence category. The Ministry's licensing guide asks for the final architectural design to be submitted [5], and the Ministry works with the municipal authorities and Civil Defence on facility licensing [8], so those approvals run alongside.
Two staffing requirements belong in the plan from the start. A private hospital must have a qualified Saudi medical director and a Saudi managing director [5]. And each role carries its own Saudisation rate: since 2025, for example, 65 per cent for hospital pharmacy roles [9], 65 per cent for radiology, 70 per cent for laboratories and 80 per cent for physiotherapy [10]. These rates shape recruitment lead times and staff cost.
4. Inspection and the final licence
Facilities that are not on the immediate-licence list receive their final licence only after an inspection committee has visited and approved the facility [11]. The final licence is issued, renewed and transferred through Seha [12]. In the programme, allow time between practical completion and the inspection for commissioning, recruitment and corrections.
5. Accreditation
The Saudi Central Board for Accreditation of Healthcare Institutions (CBAHI) is the national body that accredits government and private facilities, and the Ministry requires facilities to apply its national standards [13]. Designing policies, staffing and the building to those standards from the outset is cheaper than adapting them after opening.
6. Insurers
Most private hospital revenue comes from insured patients, and more than 13 million people hold private health insurance [14]. After the final licence, a facility applies to the Council of Health Insurance for accreditation [15], then negotiates contracts and prices with individual insurers. Until those contracts are in place, the hospital is treating mainly self-pay patients, which is why insurer timing belongs in the ramp-up.
What this means for the business case
- The opening date depends on approvals as much as on construction. Listed groups typically announce a hospital several years before it opens [16].
- Ownership and the licence category should be settled before design starts.
- Saudi leadership roles and Saudisation rates belong in the staffing plan and the staff cost line.
- Revenue in the first months depends on how quickly insurer contracts are signed.
Questions we're asked
Can a foreign company own a private hospital in Saudi Arabia?
Yes. Foreign investors may own hospitals outright, after registering with the Ministry of Investment. Check the rules for any clinics or centres attached to the hospital separately.
Who issues the licence?
The Ministry of Health, through its Seha platform. Accreditation is by CBAHI, and insurer accreditation by the Council of Health Insurance.
Sources
- Simmons & Simmons, Foreign investment relaxation in the Saudi healthcare sector, January 2019
- Oxford Business Group, Private expansion: regulatory reforms and targeted PPPs strengthen private sector participation, 2025
- Saudi Gazette, Owner of private health firms must be full-time Saudi doctor, February 2023
- Baker McKenzie, Saudi Arabia: publication of the Saudi Investment Law's Implementing Regulations
- Ministry of Health, Healthcare Investor Licensing Guide
- Hazim Al Madani Law Firm, Investors' health licenses in Saudi Arabia
- Ministry of Health, MOH Issues the Investor Guide to Health Facility Licensing (2023)
- Ministry of Health, MOH Introduces Immediate Healthcare Licenses, September 2018
- Argaam, HRSD Ministry decides to raise Saudization rates in 269 private sector professions, January 2025
- Arab News, First phase of Saudization in healthcare professions starts today, April 2025
- Ministry of Health, FAQs for Healthcare Licensing Service
- Ministry of Health, Healthcare Licensing Services
- Ministry of Health, CBAHI and MOH symposium on clinical audit, February 2015
- Argaam, CHI says private health insurance beneficiaries reach 13M, January 2025
- Zavis, How to open a clinic in Saudi Arabia (licensing steps on Seha and CHI accreditation)
- Argaam, Sulaiman Al Habib board approves SAR 571M Al-Jubail Hospital project, August 2025